Management of Mittel Rhein AG of Kln, Germany, would like to reduce the amount of...
70.2K
Verified Solution
Link Copied!
Question
Accounting
Management of Mittel Rhein AG of Kln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported:
A. Compute the throughput time.
B. Compute the manufacturing cycle efficiency (MCE) for the quarter.
C. What percentage of the throughput time was spent in nonvalue-added activities?
D. Compute the delivery cycle time.
E. If by using Lean Production all queue time during production is eliminated, what will be the new MCE?
Inspection time Wait time (from order tostart of production) Process time Move time Queue time 0.7 day 15.3 days 2.8 days 0.6 day 3.7 days
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!