Microsoft Project Case:
Shoreline Stadium Case
The G&E Company is preparing a bid to build the new47,000-seat Shoreline baseball stadium. The construction must starton July 1, 2020, and be completed in time for the start of the 2023season in April. A penalty clause of $250,000 per day of delaybeyond April 1st is written into the contract.
Percival Young, the president of the company, expressed optimismat obtaining the contract and revealed that the company could netas much as $3 million on the project. He also said if they weresuccessful, the prospects of future projects are bright since thereis a projected renaissance in building classic ball parks withmodern luxury boxes.
Questions:
Given the information provided in Table 6.3,using any project network computer program available to you toconstruct a network schedule for the stadium project and answer thefollowing questions:
- Will the project be able to be completed by the April 3deadline? How long will it take?
- What is the critical path for the project?
- Based on the schedule would you recommend that G&E pursuethis contact? Why? Include a one-page Gantt chart for the stadiumschedule.
TABLE 6.3 Shoreline StadiumCase
ID | Activity | Duration | Predecessor(s) |
1 | Baseball Stadium | | |
2 | Clear stadium site | 70 days | — |
3 | Demolish building | 30 days | 2 |
4 | Set up construction site | 70 days | 3 |
5 | Drive support piling | 120 days | 4 |
6 | Pour lower concrete bowl | 120 days | 5 |
7 | Pour main concourse | 120 days | 6 |
8 | Install playing field | 90 days | 6 |
9 | Construct upper steel bowl | 120 days | 6 |
10 | Install seats | 140 days | 9 |
11 | Build luxury boxes | 90 days | 9 |
12 | Install jumbotron | 30 days | 9 |
13 | Stadium infrastructure | 120 days | 9 |
14 | Construct steel canopy | 75 days | 10 |
15 | Light installation | 30 days | 10 |
16 | Build roof supports | 90 days | 4 |
17 | Construct roof | 180 days | 16 |
18 | Install roof tracks | 90 days | 14 |
19 | Install roof | 90 days | 17, 18 |
20 | Inspection | 20 days | 8, 11, 13, 15, 19 |
Attach the Microsoft Project file or a screenshot of theGantt chart.
Thank you, I will give you thumbs up!