Naner Corporation is trying to determine how long it takes for one product to pass...

50.1K

Verified Solution

Question

Accounting

Naner Corporation is trying to determine how long it takes for one product to pass through the production process. The following information was gathered regarding how many days the product spent in various production activities:

Activity Number of days

Inspection 5

Storage 6

Assembly 3

Handling 2

Painting 3

Packaging 1

A-which of the above activities are value added?

B-What is Nanner's total cycle time?

C-Determine Nanner's manufacturing efficiency ratio?

D-If Nanner implements a total quality management program and a just in time inventory system which of the above activities could be eliminated? What would be the change in Nanner's manufacturing efficieny ratio?

Could you please show how you came up with the calculations for the answer? I must show that when submitting this assignment. Thank you so much

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Zin AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students