Nine observations from a work measurement study using continuous timing are shown below. Allowances are determined as: personal, seven percent; fatigue, six percent; delay, six percent. Use the Work Measurement Excel template to determine the standard time for this operation.
Work
Observation
Element
1
2
3
4
5
6
7
8
9
Performance Rating
A
0.11
0.15
0.09
0.08
0.12
0.11
0.16
0.15
0.16
95%
B
0.24
0.21
0.22
0.22
0.26
0.25
0.29
0.25
0.25
115%
C
0.46
0.48
0.46
0.45
0.50
0.50
0.48
0.46
0.49
90%
D
0.64
0.67
0.65
0.62
0.72
0.70
0.70
0.67
0.73
100%
E
0.71
0.76
0.72
0.70
0.80
0.82
0.77
0.79
0.82
85%
F
1.00
1.05
0.99
1.01
1.08
1.10
1.05
1.09
1.09
100%
Round your answer to two decimal places.
minutes
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!