On February Kellers Fruity Construction Company entered into a threeyear construction contract to build a bridge for a price of $ During costs of $ were incurred, with estimated costs of $ yet to be incurred. Billings of $ were sent, and cash collected was $
In costs incurred were $ with remaining costs estimated to be $ billings were $ and $ cash was collected. The project was completed in after additional costs of $ were incurred. The companys fiscal yearend is December This project does not qualify for revenue recognition over time.
Required:
Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years.
a Prepare journal entries for to record the transactions described credit "Cash, Materials, etc." for construction costs incurred
b Prepare journal entries for to record the transactions described credit "Cash, Materials, etc." for construction costs incurred
a Prepare a partial balance sheet to show the presentation of the project as of December
b Prepare a partial balance sheet to show the presentation of the project as of December
I only need Req. B and I can't figure out the accounts receivable and billings in excess of CIP amount. I got for the accounts receivable for Req B but it's marked as wrong. The billings in excess of CIP I have no clue.
So someone helped me and said it's for both but it's wrong...... When I said it wasn't for the accounts receivable. Please help