Orange, Inc. has identified the following cost drivers for its expected overhead costs for the year:
Total overhead budgeted = $200,000
Total direct labor hours budgeted = 2,000 hours
Actual direct labor hours worked on Job 21 = 100
Actual direct materials = $5,000 total
Actual direct labor = $3,000 total
Actual units completed = 100
The totoal cost of Job 21 is:
| a. | $ 22,500 |
| b. | $ 16,000 |
| c. | $ 18,000 |
| d. | $ 19,900 |
The Total Cost of Job 21 per Unit is:
| a. | $ 60 |
| b. | $ 70 |
| c. | $ 90 |
| d. | $ 180 he Overhead Applied to Job 21 is: | a. | $ 25,000 | | b. | $ 42,000 | | c. | $ 36,000 | | d. | $ 10,000 | |