Ostler Hotel bases its budgets on guest-days. The hotel's static budget for April appears below:
| | |
Budgeted number of guest-days | | 8,700 |
Budgeted variable overhead costs: | | |
Supplies (@$7.00 per guest-day) | $ | 60,900 |
Laundry (@$3.80 per guest-day) | | 33,060 |
Total variable overhead cost | | 93,960 |
Budgeted fixed overhead costs: | | |
Wages and salaries | | 80,910 |
Occupancy costs | | 38,280 |
Total fixed overhead cost | | 119,190 |
Total budgeted overhead cost | $ | 213,150 |
|
The total overhead cost at an activity level of 9,700 guest-days per month should be:
Answer & Explanation