Penner Builders contracted to build a high-rise for $35,000,000. Construction began in 2021 and is expected to be completed in 2023. Data for 2021 and 2022 are:

2021 2022

Costs incurred to date $4,500,000 $13,000,000

Estimated costs to complete 18,000,000 12,000,000

Penner uses the percentage-of-completion method.

Instructions

(a) How much gross profit should be reported for 2021? Show your computation.

(b) How much gross profit should be reported for 2022?

(c) Make the journal entry to record the revenue and gross profit for 2022.

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students