Please provide a step-by-step solution, with\"Given:\",\"Find:\", and\"Solution:\" format, for the problembelow. Please be sure to include any tables, values, and referencesrequired to arrive at the solution you provide so that the processmay be repeated for other values.
Horizontal Formwork Design
Given: 6 in structural steel-concrete floorslab. Use ¾ in Class I plyform parallel to the span for thesheathing and Southern Yellow Pine #2 for the rest of the lumber.Joists will be 2x8 and stringers will be 6x8. Unsupported height ofshores will be 10 ft and they will be S4S. The maximum deflectionfor sheathing may be taken as 1/360 of the span. Motorized buggieswill be used to transport normal weight concrete.
Find: Design the formwork for this slab.
Solution: Show all your work.