Pre-Assessment for Manager Budget & Business Planning 16th May, 2023 Case Study: XYZ Construction...

70.2K

Verified Solution

Question

Accounting

Pre-Assessment for Manager Budget & Business Planning

16th May, 2023

Case Study: XYZ Construction Company XYZ Communication Nigeria Company is a Techco company specializes in providing Technology platform for Banks and Corporate organization. The company is planning to build a new Data Centre in Owo, Ondo State Nigeria and all the four CPUs must come together to produce the budget for the Data Centre. The project will take 3 years to be completed and the contractor will support the platform using Manage Service Operation for the first two years after the platform is delivered.

As the Budget and Business Planning Manager, you have been tasked with a responsibility of preparing a comprehensive budget for the project, instituting budgetary controls, and managing any potential contract price variations during the project's life. In your meeting with the CPUs, the following information were presented;

  1. Contract Name: Owo Data Centre
  2. Project Duration/Contract Period: January 2024 - December 2026 (3 years).
  3. Purchase Order will be issued every January
  4. In order to manage the Fx impact, payment will be made upfront twice in the year (January and July) and the exchange rate below (Table 1) have been agreed with the supplier.
  5. It is assumed that the platform has 10 years life span.
  6. 10 banks already signify interest and have signed contract with XYZ. Contract price is N100m pa (each bank) effective January 1st, 2027
  7. You have received the RFI in Table 2 below from the supplier.
    1. All Civil works will be done and completed in year 1
    2. All IDC materials will be delivered in year 2. Installation is the last phase of the project.

Table 1- Exchange Rate Table agreed with the Supplier

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2024 449 457 458 459 460 461 465 467 469 471 473 475
2025 461 465 467 469 471 473 475 477 479 481 483 485
2026 471 473 475 477 479 481 483 485 487 489 491 493
2027 485 487 489 491 493 495 497 499 501 503 505 507
2028 497 499 501 503 505 507 509 511 513 515 517 519

Table 2 (RFI received from the supplier)

Data Centre Items
1 Annual Routine Maintenance $265,130
2 Annual Platform Managed Service Operation (MSO) $120,000
3 Other annual Miscellaneous Items (Operational) $60,000
4 Project Nephos - Cloud Consumption (implemented before commissioning) $16,308
5 Critical databases Platform (implemented before commissioning) $160,000
6 3 plots of land for the Data Centre $150,000
7 Civil work for IDC Phase1B Service $254,420
8 IDC-Equipment Room_Prefab Container $172,154
9 IDC-Power Room_Prefab Container $172,154
10 IDC-Power Room_Battery for IT UPS $100,351
11 Freight and Insurance (CIF Lagos, by sea) $69,688
12 Installation and commissioning $150,000

Task

  1. Prepare
    1. Monthly Opex budget for the relevant years
    2. Capex budget for all the relevant years. 50 marks
  2. What is your budgeted EBIT in the first year of operation? 20 marks
  3. What is the ROI % based on the available information? 15 marks
  4. What additional document will you request for if you must accept payment in advance. 5 Marks
  5. Highlight steps you will take in ensuring the budget for the project is submitted for approval at due date. 10 Marks

Submit your report in a PowerPoint and all your workings in excel.

1 hour

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students