Pre-Assessment for Manager Budget & Business Planning 16th May, 2023 Case Study: XYZ Construction...
70.2K
Verified Solution
Link Copied!
Question
Accounting
Pre-Assessment for Manager Budget & Business Planning
16th May, 2023
Case Study: XYZ Construction Company XYZ Communication Nigeria Company is a Techco company specializes in providing Technology platform for Banks and Corporate organization. The company is planning to build a new Data Centre in Owo, Ondo State Nigeria and all the four CPUs must come together to produce the budget for the Data Centre. The project will take 3 years to be completed and the contractor will support the platform using Manage Service Operation for the first two years after the platform is delivered.
As the Budget and Business Planning Manager, you have been tasked with a responsibility of preparing a comprehensive budget for the project, instituting budgetary controls, and managing any potential contract price variations during the project's life. In your meeting with the CPUs, the following information were presented;
Contract Name: Owo Data Centre
Project Duration/Contract Period: January 2024 - December 2026 (3 years).
Purchase Order will be issued every January
In order to manage the Fx impact, payment will be made upfront twice in the year (January and July) and the exchange rate below (Table 1) have been agreed with the supplier.
It is assumed that the platform has 10 years life span.
10 banks already signify interest and have signed contract with XYZ. Contract price is N100m pa (each bank) effective January 1st, 2027
You have received the RFI in Table 2 below from the supplier.
All Civil works will be done and completed in year 1
All IDC materials will be delivered in year 2. Installation is the last phase of the project.
Table 1- Exchange Rate Table agreed with the Supplier
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
2024
449
457
458
459
460
461
465
467
469
471
473
475
2025
461
465
467
469
471
473
475
477
479
481
483
485
2026
471
473
475
477
479
481
483
485
487
489
491
493
2027
485
487
489
491
493
495
497
499
501
503
505
507
2028
497
499
501
503
505
507
509
511
513
515
517
519
Table 2 (RFI received from the supplier)
Data Centre Items
1
Annual Routine Maintenance
$265,130
2
Annual Platform Managed Service Operation (MSO)
$120,000
3
Other annual Miscellaneous Items (Operational)
$60,000
4
Project Nephos - Cloud Consumption (implemented before commissioning)
$16,308
5
Critical databases Platform (implemented before commissioning)
$160,000
6
3 plots of land for the Data Centre
$150,000
7
Civil work for IDC Phase1B Service
$254,420
8
IDC-Equipment Room_Prefab Container
$172,154
9
IDC-Power Room_Prefab Container
$172,154
10
IDC-Power Room_Battery for IT UPS
$100,351
11
Freight and Insurance (CIF Lagos, by sea)
$69,688
12
Installation and commissioning
$150,000
Task
Prepare
Monthly Opex budget for the relevant years
Capex budget for all the relevant years. 50 marks
What is your budgeted EBIT in the first year of operation? 20 marks
What is the ROI % based on the available information? 15 marks
What additional document will you request for if you must accept payment in advance. 5 Marks
Highlight steps you will take in ensuring the budget for the project is submitted for approval at due date. 10 Marks
Submit your report in a PowerPoint and all your workings in excel.
1 hour
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!