Problem 1:As the financial manager of the firm, you are given 6 future projects with their expected cost and yearly profits.YearProject AProject BProject CProject DProject E0-$500,000.00-$400,000.00-$300,000.00-$200,000.00-$100,000.001$135,000.00$112,500.00$90,000.00$57,500.00$30,000.002$145,000.00$125,000.00$90,000.00$62,500.00$32,000.003$155,000.00$130,000.00$90,000.00$67,500.00$34,000.004$165,000.00$135,000.00$90,000.00$70,000.00$36,000.005$175,000.00$140,000.00$90,000.00$72,500.00$38,000.00Calculate the NPV for each project if the company has a 10% discount rateCalculate the IRR for each project if you can finance and reinvest at 10%Your firm has a budget constraint of $800,000. Based on this constraint, which projects should the company implement?