Problem 12-9
Assume that you are the manager of a shop that assembles powertools. You have just received an order for 60 chain saws, which areto be shipped at the start of week 8. Pertinent information on thesaws is
Item | Lead Time (weeks) | On Hand | Components |
Saw | 2 | 15 | | A(2), B(1), C(4) |
A | 1 | 10 | | E(3), D(1) |
B | 2 | 5 | | D(2), F(3) |
C | 2 | 65 | | E(2), D(2) |
D | 1 | 20 | | |
E | 1 | 10 | | |
F | 2 | 30 | | |
|
Develop the material requirements plan for component E usinglot-for-lot ordering. (Leave no cells blank - be certain toenter "0" wherever required.)
Item: E(3) & E(2) LT = 1 wk. | Beg. Inv. | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | | | | | | | | | |
Scheduled receipts | | | | | | | | | |
Projected on hand | | | | | | | | | |
Net requirements | | | | | | | | | |
Planned order receipt | | | | | | | | | |
Planned order release | | | | | | | | | |
|