High Desert Potteryworks makes a variety of pottery products that it sells to retailers. The company uses a job-order costing system in which departmental predetermined overhead rates are used to apply manufacturing overhead cost to jobs. The predetermined overhead rate in the Molding Department is based on machine-hours, and the rate in the Painting Department is based on direct labor-hours. At the beginning of the year, the company provided the following estimates:
Department
Molding
Painting
Direct labor-hours
34,500
54,500
Machine-hours
84,000
32,000
Fixed manufacturing overhead cost
$ 252,000
$ 495,950
Variable manufacturing overhead per machine-hour
$ 2.40
-
Variable manufacturing overhead per direct labor-hour
-
$ 4.40
Job 205 was started on August 1 and completed on August 10. The company's cost records show the following information concerning the job:
Department
Molding
Painting
Direct labor-hours
74
125
Machine-hours
310
68
Direct materials
$ 944
$ 1,160
Direct labor cost
$ 690
$ 1,000
Required:
1. Compute the predetermined overhead rates used in the Molding Department and the Painting Department.
2. Compute the total overhead cost applied to Job 205.
3-a. What would be the total manufacturing cost recorded for Job 205?
3-b. If the job contained 38 units, what would be the unit product cost?
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!