Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $5,140,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the contract were as follows:
At 12-31-2018
At 12-31-2019
At 12-31-2020
Percentage of completion
10%
60%
100%
Cost Incurred to Date
445000
3260000
5599000
Estimated Costs to Complete
3340000
2270000
0
Billings to AxelRod, to date
1005000
2550000
5140000
Compute gross profit or loss to be recognized as a result of this contract for each of the three years. AND
Assuming Curtiss recognizes revenue over time according to percentage of completion, compute gross profit or loss to be recognized in each of the three years.
Gross Profit (Loss) Recognized "Upon Completion"
Gross Profit (Loss) Recognized "Over Time"
2018
$
2019
2020
Total Project Profit(Loss)
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!