Q2) what are liquidated damages? Why to include a liquidated
damages clause in the contract? Are...
70.2K
Verified Solution
Link Copied!
Question
Civil Engineering
Q2) what are liquidated damages? Why to include a liquidateddamages clause in the contract? Are they enforceable? How tocalculate the amount of liquidated damage?
Answer & Explanation
Solved by verified expert
3.8 Ratings (365 Votes)
Liquidated damages also referred to as liquidated and ascertained damages are damages whose amount the parties designate during the formation of a contract for the injured party to collect as compensation upon a specific breach An exampleLiquidated damages
See Answer
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!