Question
pts
A residential project has the following information:
Four major activities are scheduled across a month time span shown in the below bar chart
Assuming the monthly indirect cost ie site office costs, telephone, heat, light, and supervisory salaries is $
Assuming the direct costs are evenly distributed across the duration of the activity
What is the total cost at month A residential project has the following information:
Four major activities are scheduled across a month time span shown in the below bar chart
Assuming the monthly indirect cost ie site office costs, telephone, heat, light, and supervisory salaries is $
Assuming the direct costs are evenly distributed across the duration of the activity