QUESTION 21 To complete the first setup on a new machine took an employee 100 minutes. Using an 80% cumulative average-time learning curve indicates that the second setup on the machine is expected to take: A. 30 minutes B. 40 minutes C. 60 minutes D. 80 minutes QUESTION 21 To complete the first setup on a new machine took an employee 100 minutes. Using an 80% cumulative average-time learning curve indicates that the second setup on the machine is expected to take: A. 30 minutes B. 40 minutes C. 60 minutes D. 80 minutes
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!