Question 4 Project management (20 marks) Paige Turned recently purchased a block of land...

60.1K

Verified Solution

Question

Accounting

Question 4 Project management (20 marks)

Paige Turned recently purchased a block of land to building a new multi-million dollar manufacturing plant. The current facility (a converted chemical shed) is consistently causing problems. The new purpose-built facility would allow Picasso to increase production and satisfy safety and environmental regulations.

A building consultant has broken the project into a number of separate tasks identified by letters. Preliminary estimates of the normal time and cost have been provided:

Task

Task description

Time (days)

Cost ($)

Crash time (days)

Per day revised costs ($)

A

Preparation of drawings and permits

14

72,500

10

10,000

B

Calling and letting of tenders

68

166,750

66

23,000

C

Site preparation and excavation

6

116,000

4

16,000

D

Pouring the foundation

24

250,000

24

-

E

Framing

40

145,000

30

20,000

F

Plumbing and electrical work

18

159,500

12

22,000

G

Interior finished

16

108,750

12

15,000

H

Exterior finishes

22

175,000

22

-

I

Installing and commissioning new machines

34

101,500

30

14,000

J

Finishing touches and final work through

32

64,000

32

-

The building consultant has advised that the following relationship exists among these tasks:

A and B can be commenced at the same time.

C and D can both be commenced as soon as A is completed.

E cannot be commended until C and D are completed.

F can be commenced once D is completed.

G can be started once F is finished.

H cannot be commenced until E and G are completed.

I cannot start until B and E are completed.

J cannot commence until H and I are completed.

Required:

  1. Using an appropriate computer drawing program, draw the network diagram for the project showing the task letter on the activity paths. (3 marks)
  2. Identify all the possible pathways and determine the critical path. (2 marks)
  3. Calculate the minimum time and associate cost in which the project could be completed. (8 marks)
  4. The building is nearing completion, Paige Turner has written into the contract penalty provisions if the work is not finished on time. The only remaining task to complete is J and so far it is on schedule to complete in time however there is still 12 days to go, the cost has increased from $2,000 per day to $3,500 per day. The building consultant, in discussion with Paige, feels that an investigation might be worthwhile. The cost to investigate is $4,000 per day which might show if there is a problem and if this is the case it can be rectified by $10,000. This would lead to the cost being reduced to $2,000 for the remaining days. The probability of being able to rectify the problem is 0.7, should the consultant investigate? (7 marks)

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students