Question 4 Project management (20 marks) Paige Turned recently purchased a block of land...
60.1K
Verified Solution
Link Copied!
Question
Accounting
Question 4 Project management (20 marks)
Paige Turned recently purchased a block of land to building a new multi-million dollar manufacturing plant. The current facility (a converted chemical shed) is consistently causing problems. The new purpose-built facility would allow Picasso to increase production and satisfy safety and environmental regulations.
A building consultant has broken the project into a number of separate tasks identified by letters. Preliminary estimates of the normal time and cost have been provided:
Task
Task description
Time (days)
Cost ($)
Crash time (days)
Per day revised costs ($)
A
Preparation of drawings and permits
14
72,500
10
10,000
B
Calling and letting of tenders
68
166,750
66
23,000
C
Site preparation and excavation
6
116,000
4
16,000
D
Pouring the foundation
24
250,000
24
-
E
Framing
40
145,000
30
20,000
F
Plumbing and electrical work
18
159,500
12
22,000
G
Interior finished
16
108,750
12
15,000
H
Exterior finishes
22
175,000
22
-
I
Installing and commissioning new machines
34
101,500
30
14,000
J
Finishing touches and final work through
32
64,000
32
-
The building consultant has advised that the following relationship exists among these tasks:
A and B can be commenced at the same time.
C and D can both be commenced as soon as A is completed.
E cannot be commended until C and D are completed.
F can be commenced once D is completed.
G can be started once F is finished.
H cannot be commenced until E and G are completed.
I cannot start until B and E are completed.
J cannot commence until H and I are completed.
Required:
Using an appropriate computer drawing program, draw the network diagram for the project showing the task letter on the activity paths. (3 marks)
Identify all the possible pathways and determine the critical path. (2 marks)
Calculate the minimum time and associate cost in which the project could be completed. (8 marks)
The building is nearing completion, Paige Turner has written into the contract penalty provisions if the work is not finished on time. The only remaining task to complete is J and so far it is on schedule to complete in time however there is still 12 days to go, the cost has increased from $2,000 per day to $3,500 per day. The building consultant, in discussion with Paige, feels that an investigation might be worthwhile. The cost to investigate is $4,000 per day which might show if there is a problem and if this is the case it can be rectified by $10,000. This would lead to the cost being reduced to $2,000 for the remaining days. The probability of being able to rectify the problem is 0.7, should the consultant investigate? (7 marks)
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!