Question 5: (10 Marks) For the following information given on a project: Activity Predecessor Activity...

60.1K

Verified Solution

Question

Accounting

Question 5: (10 Marks) For the following information given on a project: Activity Predecessor Activity Normal Time (Weeks) Crash Time (Weeks) Normal Cost ($) Crash Cost ($) A - 20 19 8,000 10,000 B - 15 13 16,000 20,000 C A 22 20 13,000 14,000 D A 17 15 7,500 9,000 E B 19 17 4,000 6,000 F C 28 27 3,000 4,000 G D, E 25 24 12,000 13,000 Determine: 1) The critical path 2) The cost slope for each activity.

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students