Read the Scenario below and answer the questions thatfollow.
You are working on a project to implement an online benefitsmanagement portal to enable employees to have a “one stop†locationto view their health and dental benefits, get answers tobenefits-related questions, and enable for changes to be made tohealth benefit coverage. Requirements were gathered over a two-weektime period at the start of the project and all stakeholdersparticipated in requirements gathering sessions. The project isnear completion – the portal has been developed by theIT/Application Development group. It has been tested, works welland will be rolled out early next week. You are approached by amember of the senior leadership team who suggests that it would beof value to add in a component so that employees can also managetheir 401Ks. In fact, he wants this to happen in time for this rollout.
Question 1[ 20 marks]
Keeping the project triple constraints in mind, elaborate on theeffects of adding extra components to the portal by your SeniorLeaders.