San Juan, Inc. is considering two alternatives: A and B. The costs associated with the alternatives are listed below:
| Alternative A | | Alternative B |
Material costs | $ | 35,000 | | | $ | 60,000 | |
Processing costs | | 40,000 | | | | 60,000 | |
Building costs | | 13,100 | | | | 30,000 | |
Equipment rental | | 20,100 | | | | 20,100 | |
|
If only the differential costs of the two decisions are considered, the total cost of Alternative B is
$139,150.
$61,900.
$108,200.
$170,100.
Answer & Explanation
Solved by verified expert