Sarno Corporation has an activity-based costing system with three activity cost pools- Processing, Batch Setup, and Other. Costs in the Processing cost pool are assigned to products based on machine-hours (MHs) and costs in the Batch Setup cost pool are assigned to products based on the number of batches. Costs in the Other cost pool are not assigned to products. Data concerning the two products and the company's costs and activity-based costing system appear below:
Activity Cost Pools
Processing
$3,000
Batch Setup
$9,800
Other
$9,200
MHs
Batches
Product #1
5,800
700
Product #2
4,200
300
Total
10,000
1,000
Product #1
Product #2
Sales (total)
$45,300
$48,400
Direct materials (total)
$19,600
$16,900
Direct labor (total)
$15,900
$24,200
Required:
a. Calculate activity rates for each activity cost pool using activity-based costing.
b. Determine the amount of overhead cost that would be assigned to each product using activity-based costing.
c. Determine the product margins for each product using activity-based costing.
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!