Scatter Diagrams and High-Low Cost Estimation Assume the local Pearle Vision has the following information...
80.2K
Verified Solution
Link Copied!
Question
Accounting
Scatter Diagrams and High-Low Cost Estimation Assume the local Pearle Vision has the following information on the number of sales orders received and order-processing costs.
Month
Sales Orders
Order-Processing Costs
1
3,000
$ 49,620
2
1,500
30,225
3
4,400
72,420
4
2,800
49,140
5
2,300
41,865
6
1,200
25,860
7
2,000
37,500
Required (a.) Use information from the high- and low-volume months to develop a cost-estimating equation for monthly order-processing costs.
(b.) Plot the data on a scatter diagram. Using the information from representative high-and low-volume months, develop a cost estimating equation for monthly production costs. If needed, an Excel worksheet is provided in the following link in order to create the scatter diagram:
Month
Sales Orders
Order-Processing Costs
1
3,000
$ 82,700
2
1,500
50,375
3
4,400
120,700
4
2,800
81,900
5
2,300
69,775
6
1,200
43,100
7
2,000
62,500
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!