Solve the following Problem: for the following operation of manufacturing a machining vise use the process batch and reduce the lead time.
Vise Body Movable Jaw Upper Guide Plate Lower Guide Plate
Rough cut top 4 min Rough cut 3 min Rough cut 3 min Rough cut 3 min
Rough cut bottom 2 min Finish cut 3 min Finish cut 3 min Finish cut 3 min
Finish cut top 4 min
Finish cut bottom 2 min