Soundex produces two models of satellite radios. Model Arequires 15 minutes of work on Assembly Line I and 10 minutes ofwork on Assembly Line II. Model B requires 10 minutes of work onAssembly Line I and 12 minutes of work on Assembly Line II. At most25 hours of assembly time on Line I and 22 hours of assembly timeon Line II are available each day. Soundex anticipates a profit of$12 on Model A and $10 on Model B. Because of previousoverproduction, management decides to limit the production of ModelA satellite radios to no more than 80 per day.
Find the range of values that the resource associated with thetime constraint on Assembly Line I can
assume.