The answer are 63000000 and 77000000 respectively. Could you please show the calculation Entity A...
90.2K
Verified Solution
Link Copied!
Question
Accounting
The answer are 63000000 and 77000000 respectively. Could you please show the calculation
Entity A started a three-year contract to build a new office building on 1 April 2020. The contract had a fixed price of $90,000,000. The entity will satisfy the performance obligation over time.
The entity incurred costs to 31 March 2021 of $77,000,000 and estimated that a further $33,000,000 would need to be spent to complete the contract.
The entity measures the progress of contracts using work completed compared to the contract price.
At 31 March 2021, a surveyor valued the work completed to date at $63,000,000.
REQUIRED:
Measure the contract revenue and the contract cost in the Statement of Profit or Loss for the year ended 31 March 2021 respectively.
ANSWER:
Contract revenue = $[1]
Contract cost = $[2]
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!