The Beast Company reports the following times required to complete an order:
Wait time = 13.6 hours
Queue time = 4.4 hours
Move time = 2.9 hours
Process time = 1.2 hours
Inspection time = 0.4 hours
Manufacturing cycle efficiency is closest to:
a.) 5% b.) 13% c.) 18% d.) 51%