Transcribed Image Text
The following are the cash flows of two projects:YearProject AProject B0?$330 ?$330 1160 230 2160 230 3160 230 4160 a.Calculate the NPV for both projects if the opportunity cost ofcapital is 17%. (Do not round intermediate calculations.Round your answers to 2 decimal places.)ProjectNPV A$ B b.Suppose that you can choose only one of these projects. Whichwould you choose?Project AProject BNeither