The following data have been recorded for recently completed Job 674. Direct materials cost was...
90.2K
Verified Solution
Link Copied!
Question
Accounting
The following data have been recorded for recently completed Job 674. Direct materials cost was $1,293. A total of 28 direct labor hours were worked on the job. The direct labor wage rate is $15 per labor-hour. The company applies manufacturing overhead on the basis of direct labor hours. The predetermined overhead rate is $5 per direct labor hour.
The total product cost for the job would be:
O $1,713
0 $1,853
O $1,825
O $1,773
Using the predetermined overhead rate, the company would have applied a total amount of -----manufacturing overhead to various jobs during the period
0 $288,036
O $267,000
0 $320,560
O $315,000
What was the overapplied or underapplied overhead for the year?
A $55,560 overapplied
B $48.000 underapplied
C $55,560 underapplied
D $48,000 overapplied
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!