The following information is available regarding the total manufacturing overhead of Olaf Company for a recent four-month period.
| Machine Hours | | Mfg. Overhead |
April | 70,000 | | $ | 176,000 | |
May | 50,000 | | $ | 159,000 | |
June | 105,000 | | $ | 219,500 | |
July | 101,000 | | $ | 187,000 | |
|
Using the high-low method, compute the variable element of manufacturing overhead cost per machine hour.
-
$2.27 per machine hour
-
$1.10 per machine hour
-
$.35 per machine hour
-