The following jobs are waiting to be processed at Rick? Solano'smachine center.? Solano's machine center has a relatively longbacklog and sets a fresh schedule every 2? weeks, which does notdisturb earlier schedules. Below are the jobs to be scheduled?today, which is day 241 ?(day 241 is a work? day). Job names referto names of clients and contract numbers. Compute all times basedon initiating work on day 241.
(Job) (Date Job Received) (Due Date Duration (days))
BR-02 225 270 25
CX-01 230 320 35
DE-06 235 360 40
RG-05 231 310 30
SY-11 228 300 15
Using the FCFS? (first come, first? served) decision rule forsequencing the jobs, the order is:
The average tardiness (job lateness) for the sequence developedusing the FCFS rule? =
The percentage utilization for the sequence developed using theFCFS rule?
The average completion time for the sequence developed using theFCFS rule?
The average number of jobs in the system for the sequencedeveloped using the FCFS rule? =