The following table contains a list of activities, with precedence requirements and crash costs. All...
60.1K
Verified Solution
Link Copied!
Question
Accounting
The following table contains a list of activities, with precedence requirements and crash costs. All start and finish times and crash costs are on a per -week basis.
Determine the project cost and duration without crashing.
Determine the least expensive project cost if the duration is to be 10% shorter than normal project duration.
Determine the least expensive project cost if the duration is to be 20% shorter than normal project duration.
Create a graph that shows project expediting cost plotted as a function of the reduction in project
duration.
Activity
Normal
Time
Crash
Time
Normal
Cost
Crash Cost
Predecessor
A
10
7
2000
2600
B
12
8
1500
2000
A
C
16
12
2200
3000
A
D
8
7
2500
3000
B
E
13
10
1950
2275
C
F
9
8
800
1000
D
G
24
29
3650
4000
E, F
H
17
14
1200
1800
G
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!