The project budget baseline for XYZ is $3,500,000 with thefollowing risks assessment: Risk Event Probability Impact ExpectedValue Parts delayed in Customs 40% $100,000 Strong labor trainingequates to quick assembly 60% ($50,000) Heat sink assembly requiresrework 85% $150,000 (source: Paul Martinsen, PMP)3. Calculate the adjusted project budget baseline for XYZproject.