The Shady Farm Milk Company can
process milk at a fixed rate of 5100 gallons/hour. The...
Free
80.2K
Verified Solution
Link Copied!
Question
General Management
The Shady Farm Milk Company canprocess milk at a fixed rate of 5100 gallons/hour. The company’sclients request 94000 gallons of milk over the course of one day.This demand is spread out uniformly from 8 a.m. - 6 p.m. Thecompany starts producing at 8 a.m. and continues to work until allof the demand has been satisfied.
(Roundyour answer to 2 decimal places.)
How long does the clientrequesting milk at 6 p.m. have to wait to have their demandsatisfied?
hours
Answer & Explanation
Solved by verified expert
4.4 Ratings (638 Votes)
Waiting time for client at 6 p.m. = Available hours till 6 p.m.
* (Demand per hour Capacity per hour – 1)
Here,
Available hours till 6 p.m. = 10 hours
Demand per hour = Gallons demanded per day Available hours in
a day
= 94000 10
= 9400 gallons
Capacity per hour = 5100 gallons
So, Waiting time for client at 6 p.m. = 10 * ( 94005100 –
1)
= 8 hours (approximately)
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Zin AI - Your personal assistant for all your inquiries!