The standard factory overhead rate is $7.50 per machine hour ($6.20 for variable factory overhad...
80.2K
Verified Solution
Link Copied!
Question
Accounting
The standard factory overhead rate is $7.50 per machine hour ($6.20 for variable factory overhad and $1.30 for fixed overhead) based on 100% capacity of 80,000 machine hours. The standard cost and the actual cost of factory overhead for the production of 15,000 units during August were as follows:
Actual Variable Factory Overhead: $360,000
fixed factory overhead 104,000
Standard hours allowed for units produced: 60,000 hours
what is the amount of the factory overhead controllable variance?
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!