The tree diagram in figure below describes the uncertain cash flows for an engineering project. The analysis period is two years, and MARRequals=18% per year. Based on this information,
a. What are the E(PW), V(PW), and SD(PW) of the project?
b. What is the probability that PW 0?
Please answer all questions will rate highly if correct.
Time Period 0 1 2 $17,900 0.3 $5,000 0.2 $20,700 0.5 $22,900 0.2 $21,400 0.3 - $26,000 $13,500 0.5 0.4 $23,500 0.3 $28,900 0.3 $23,600 0.4 $18,500 0.5 $26,300 0.1 $30,400 Discrete Compounding; i = 18% Single Payment Compound Amount Uniform Series Compound Amount Factor Sinking Capital Recovery Present Present Fund Worth Factor Factor Worth Factor Factor Factor To Find F Given P To Find P Given F To Find F To Find A To Find A To Find P Given A P/A Given A Given F Given P F/A A/F F/P P/F A/P 0.8475 1.0000 1 1.1800 0.8475 1.0000 1.1800 2.1800 0.6387 2 1.3924 0.7182 1.5656 0.4587 3 1.6430 0.6086 3.5724 2.1743 0.2799 0.4599 1.9388 5.2154 2.6901 0.1917 4 0.5158 0.3717 0.1398 5 2.2878 0.4371 7.1542 3.1272 0.3198
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!