Tillman Company uses the high-low method to estimate its cost function. The information for the current year is provided below:
Machine-hours Costs
Highest observation of cost driver 2,500 $300,000
Lowest observation of cost driver 1,500 $ 220,000
What is the estimated cost function for the above data?
y = 300,000 +120X
y = 220,000 +147X
y = 100,000 +80X
y = 130X