Which of the following statements is false regarding theBluebeam software package?
| | Â Â It can be used to manage adigital document set.
|
| | It can be used to create hyperlinks between documents tosimplify navigation.
|
| | It can be used to perform on-screen takeoffs ofmaterials.
|
| | Â Â It can be used to createproject schedules.
|
In the Activity Block, the number of working days neededto perform a specific activity is called:
| | Interval |
| | Length |
| | Duration |
| | Extent |
Which of the following best describes when the successoractivity cannot start until the predecessor activity finishes (forexample: Activity B starts after the end of ActivityA)?
| | Start-to-start |
| | Finish-to-start |
| | Finish-to-finish |
| | None of the above |
In scheduling software, the least commonly usedrelationship is:
| | Finish -to-start |
| | Start-to-start |
| | Finish-to-finish |
| | Start-to-finish |
| | |
The duration assigned to a predecessor activity to delayits successor is called:
| | Lag |
| | Lead |
| | Successor |
| | First activity |
| | |
When adding or deleting doors and windows in Revit, thedoor and window schedule will automatically update.
True
False