Which one is the critical path or the longest time path?
Activity
Time
Immediate Predecessor
A.
Find client
7
---
B.
Write prospectus
2
A
C.
Obtain approval from client and professor
4
B
D.
Complete programming
12
C
E.
Do industry background research
10
F.
Write final paper
8
D, E
G.
Write oral report
5