XYZ Construction Company is using the percentageofcompletion method of accounting for longterm contracts in the company's financial statements. You have been engaged to assist XYZs controller in the preparation of a presentation to be given at the board meeting. The controller provides you with the following information:
XYZ commenced doing business on January
Construction activities for the year ended December were as follows:
Each contract is with a different customer.
Any work remaining to be done on the contracts is expected to be completed in
Required:
a Prepare a schedule by project, computing the amount of income or loss before selling, general, and administrative expenses for the year ended December which would be reported under the percentageofcompletion method based on estimated costs
b Prepare the general journal entryies to record revenue and gross profit on project Beta second project for assuming that the percentageofcompletion method is used.
c Indicate the balances that would appear in the statement of financial position at December for the following accounts for Project Delta fourth project assuming that the percentageofcompletion method is used.
Accounts Receivable
Billings on Construction in Process
Construction in Process