You are building a bus stop shelter and have been working on itfor 20 days. Your boss has asked for a status report for theproject after 20 days.
a) Fill in the missing values in the following StatusReport.
b) For the entire project, what is the current
a. Cost Performance Index, CPI = ________,
b. Schedule Performance Index, SPI = _________,
c. Cost Variance, CV = _________,
d. Schedule Variance, SV = __________.
c) Suppose that the work from this date forward will progress atplanned rates whether or not these rates have prevailed to date.What is the forecasted cost at completion (FAC) for the entireproject?
item | total budget($) | planned progress | BCWS($) | ACWP($) | ACTUAL PROGRESS | BCWP($) | CV | SV | FAC($) |
excavation | 9600 | 100% | | 9000 | 100% | | | | |
cast slab | 1800 | 100% | | 2000 | 100% | | | | |
curb | 1500 | 100% | | 1500 | 100% | | | | |
walls | 2700 | 80% | | 2500 | 100% | | | | |
paving | 1200 | 40% | | 300 | 20% | | | | |
roof trusses | 1000 | 40% | | 500 | 60% | | | | |
roofing | 600 | 10% | | 0 | 0% | | | | |
lights | 500 | 20% | | 250 | 40% | | | | |
seating | 500 | 0% | | 0 | 0% | | | | |
paint | 1000 | 0% | | 0 | 0% | | | | |