Question
Finance
You are given the choice between two mutually exclusive projects (8 points) Project A $20,000 initial investment $6,000 a year NCF for 6 years Project B $25,000 initial investment $5,300 a year in NCF for years if the cost of capital is 0%, which project should you select if you will need this capacity for the indefinite future. Explain the basis for your decision. A number one is not sufficient