You are the Owners project manager on an electrical upgrade project. Existing overhead power lines are being buried in a duct bank to hide them from view in an area of the town that is being revitalized. There are a total of 8.6 miles of power lines being buried. All the power lines being buried are on one street and run in a straight line. Due to the size of the wires, a pull box needs to be installed every 500 feet.
There are three primary activities in burying the power lines:
Dig and install pull box/conduit
Pull wires
Terminate/connect wires
Labor:
A four-man crew can install one pull box and 500 ft of conduit in 2 days.
A seven-man wire crew can test and install 1000 ft of wire per day.
A three-man electrician crew can terminate 7 connections per day.
Task
Draw an LOB diagram to illustrate how it works. Submission can be handwritten and uploaded or created on the computer.
Submit a written explanation of what the LOB is going to tell/show the contractor and why it would be useful in this application.
pls solve this urgently i will upvote 3 members
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!