Your job is to fully staff your facility at the lowest cost. Thefacility must have at least 2 people w working from 6am-8pm Mondaythru Friday and at least 1 person working from 10am to 6 pm onSaturdays. Nobody works on Sundays. Full time staff must work 8hours a day, five days a week. Part time staff work 4 hours a day,5 days a week. Nobody is allowed to work overtime. All employeesreceive the same hourly rate. What is the number of part time andfull time employees are needed in order to fully staff theoperation with the smallest total labor cost?
FT employees needed?:
PT employees needed?: