At week 24 of a project to shoot a television commercial whatshould the expenditures be? If the earned value is right onschedule but the actual expenses are $9,000, what are the cost andschedule variances? What are the three indexes, The ETC (fundsneeded to complete the project), and Expected project cost atcompletion?
Activity | Predecessor | Duration (weeks) | Budget $ |
A | - | 6 | 900 |
B | - | 6 | 1200 |
C | A | 6 | 1200 |
D | A | 12 | 1800 |
E | B, C | 14 | 1400 |
F | B, C, D | 10 | 1500 |
G | D, E | 16 | 800 |