Discuss the preparation/construction process in different
layers of highway foundation. How
determination of optimum moisture content for...
70.2K
Verified Solution
Link Copied!
Question
Civil Engineering
Discuss the preparation/construction process in differentlayers of highway foundation. How
determination of optimum moisture content for a given soilwill ensure the load carrying capacity of
highway foundation?
Answer & Explanation
Solved by verified expert
4.2 Ratings (726 Votes)
The pavement foundations mainly consist of two layers thesubbase and the base courseSubbase provides a level surface with sufficient loadbearingcapacity and acts as a temporary wearing surface course duringconstruction It is prepared by cutting Filling embankment tothe required level Generally approx 98 of the maximum drydensity of the soil should be the achieved compaction and a minimumof 8 CBR Subbase material shall be placed and compacted inlayers not exceeding 150mm to the desired
See Answer
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!