Exercise Algo Overhead controllable and volume variances LO P
Blaze Corporation allocates overhead on the basis of DLH and the standard amount per allocation base is per unit. For
March, the company planned production of units of its production capacity of units and prepared the following
budget. The company actually operated at capacity units in March and incurred actual total overhead costs of $
Compute the standard overhead rate. Hint. Standard allocation base at capacity is computed as units
per unit.
Compute the total overhead variance.
Compute the overhead controllable variance.
Compute the overhead controllable variance.
Note: Indicate the effect of the variance by selecting favorable, unfavorable, or no variance. Do not round intermediate
calculations.
Compute the overhead volume variance.
Note: Indicate the effect of the variance by selecting favorable, unfavorable, or no variance. Do not round intermediate
calculations.