McConnell Inc. contracted to build a commercial building for Pelosi Inc. The contract called for...
70.2K
Verified Solution
Link Copied!
Question
Accounting
McConnell Inc. contracted to build a commercial building for Pelosi Inc. The contract called for completion on June 1 of the current year. The price was $2,000,000.00, payable in installments at $500,000.00 on 9/1, 12/1, 3/1 and on 6/15 (two weeks after the scheduled completion date.)
McConnell was unable to complete the building until 6/18 and at that time the building met all inspection and code requirements and Pelosi was able to move in.
Included in the contract was the following provision:
Builder (McConnell) acknowledges that time is of the essence. For every day beyond the contracted, 6/1 date that the building is unavailable to Buyer (Pelosi), Buyer shall reduce payment $1500.00 per day to a maximum reduction of $60,000.00.
On July 2 Pelosi made the final payment of $474,500.00 ($500,000 - $25,500) to McConnell noting the building was delivered 17 days beyond the contracted date.
McConnell sued for the remaining payment of $25,500 arguing that he was late due to a supplier who went out of business during the project and due to a one week strike by McConnell plumbers. McConnell also indicated that the $25,500 was excessive and amounted to a penalty.
Indicate who should prevail and support your answer. Also, make sure you advance arguments for both sides.
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!