Transcribed Image Text
ProjectInitial OutlayY1Y2Y3Y4Y5A-450505050200150B-8502505010050010Projects are independent. No specific budget. The cost ofcapital is 10.9%. What project or projects should beaccepted based on the IRR?A.Project BB.BothC.Project AD.Neither