The controller for Washington Co. established the following overhead cost pools and cost drivers:
| Estimated | |
| Budgeted | | Cost Driver | |
Overhead Cost Pool | Overhead | Cost Driver | Level | |
Quality controls | $60,000 | # of inspections | 2,000 | inspections |
Machine setups | $100,000 | # of setups | 20,000 | setups |
Other overhead costs | $90,000 | # of machine hrs | 2,500 | machine hrs |
Total overhead costs | $250,000 | | | |
| | | | |
A recent order for sailboats used: | | | |
Quality inspections | 400 | inspections | | |
Machine setups | 2,500 | setups | | |
Machine hours (MHs) | 300 | machine hours |
a. What is the overhead rate per machine hour if the number of machine hours (MHs)
is used as a single cost driver under traditional costing system?
b. Utilizing traditional costing, how much overhead is assigned to the order
based on machine hours as a single cost driver?
c. Utilizing ABC, how much total overhead is assigned to the order?